You signed a contract. You forgot it has a clause that says: “Each day of delay: NIS 3,000.” Now the other side is claiming NIS 90,000 for a month of delay. Will it really get that in court?

As a rule, the clause is valid, but the court may reduce the amount (section 15(a)).

What does Israeli law say?

Section 15 of the Contracts (Remedies for Breach of Contract) Law, 5731-1970 governs liquidated damages in three subsections:

The practical result: the clause works. It saves disputes over the amount of the damage. But it is not “unchallengeable”.

Liquidated damages versus a penalty: what is the relevant difference?

English law draws a sharp line between liquidated damages (an advance estimate of damage, valid) and a penalty clause (a penalty meant to deter, unenforceable). In Israel the law does not make this distinction. Section 15(a) applies to all liquidated damages, and the question is whether the amount was set without any reasonable relation to the damage that could have been foreseen when the contract was made. A “punitive” amount, which is not an estimate of foreseeable damage, is exactly the case the power to reduce is meant for.

In a standard-form contract, even with a business and not only with a consumer, a term that sets unreasonable liquidated damages in favor of the supplier is presumed to be an unfair term (section 4(6a) of the Standard Contracts Law, 5743-1982). A court that finds the term unfair will cancel it or change it to the extent needed to remove the unfairness (section 19(a)).

When will a court reduce the amount?

Not easily. The burden is on whoever asks for the reduction. They need to show that:

A clear example: an amount that has no connection at all to the damage that could have been foreseen (for example, NIS 50,000 for a one-hour delay). On the other hand, when the amount was set in negotiations and the contract explains the basis of the calculation, it is harder to show that it has no reasonable relation to the foreseeable damage.

What should you check if you are asked to pay?

First of all, do not pay and do not ignore it. Make these checks:

Need a contract checked before you sign, or the other side is not keeping to it?I will get back to you within one business day.

Calls and replies in English or Hebrew

What happens after you write to me

  1. You write what happened and with whom. No documents.
  2. I get back to you within one business day for a short call of a few minutes.
  3. If it is a matter I handle: after the call you will receive, in writing, what will be done and what the next step is. Work starts only after you approve.

At the end of the call you will know one of three things: it is a matter I handle, and what the next step is; you can manage without a lawyer, and which guide fits; or it is outside my field, and where to turn.

How do you draft such a clause properly?

If you are the side putting the clause into the contract, a few principles will protect it:

Sources

The links lead to the original legislation (in Hebrew). The binding text is the one published in Sefer HaHukim (the official gazette of statutes).

Checklist

  • Practical tip: when representing a party sued under a liquidated damages clause, remember that the test in section 15(a) is the damage that could have been foreseen when the contract was made. So build the application for a reduction around what was foreseeable at the time of signing, not only around the damage actually caused.
  • Tactical point: in contracts between businesses (B2B), when a large supplier imposed a pre-set wording on a small contractor, this may be a standard-form contract, and then the presumption of unfairness in section 4(6a) of the Standard Contracts Law also applies. It is worth documenting the circumstances in which the contract was signed.
  • Common mistake: drafting a liquidated damages clause without an “anchor” in real damage, and finding out later that the amount was reduced. The court may reduce liquidated damages that were set without any reasonable relation to the damage that could have been foreseen when the contract was made (section 15(a) of the Contracts (Remedies for Breach of Contract) Law). One line of explanation in the body of the contract, such as “the amount was set taking X into account”, can save a lot.
Legal note: The information in this guide is general and is not legal advice or a substitute for advice on your own case. Every case is assessed on its own facts.